project involved meetings with the customer to offer several solutions
and to agree a final operational specification.
Allowing the access to all parts of the fuselage,
yet still ensuring operator safety involved many technical challenges
when designing the interlocks on the movable jigs operating in hazardous
environments.
The final design incorporated a Mitsubishi
PLC, servo-motor drives and an infra-red safety curtain. TRITEC
helped install and commission a total of ten stations and ten movable
jigs within five months. |